Adding Supplementary Information To Tasks In Project2010

In this article, I will demonstrate how copy add supplementary information to tasks in project 2010.
  • 1831

Introduction

You can give definition or explain an individual task by entering notes. Basic process to add a note to a task is given below.

Step 1

Select task on which you want to add a note.

Step 2

On the Task Tab, in the Properties group click Notes.

Step 3

In the Notes area, type the note you want to give.

Step 4

Click OK, when you are finished.

Note- A note icon is added to the Indicators column in the table area of the Gantt Chart.

NotesIndicator-in-project2010.jpg