Introduction

Process to  change the timescale in the Calendar View in Project 2010 is given below.

Step 1

On the View tab, in the Task Views group, click Calendar.

Open-calender-in-Project2010.jpg

Step 2

Right-Click on the calendar view and select timescale in drop-down list.

Step 3

In the Timescale dialog box select Week Headings Tab.

WeekHeadings-CalenderView-in-Project2010.jpg


Step 4

To add miniature calendars for the next and previous months, select the Display month pane check box.

Step 5

Now click the date boxes tab.

Step 6

Under Top row and Bottom row, select the information that you want to display in the left and right portions of each row, and then select the patterns and colors you want.