How To Level Project Schedule In Project 2010
This article shows how to level project schedule in Project 2010.
Introduction
Process for leveling Project schedule in project 2010 is given below.
Step 1
Confirm tasks are in priority order in the WBS hierarchy.
Step 2
Confirm only one resource is assigned to each task.
Step 3
Now select the Resource menu tab.
Step 4
Then select the Leveling Options from the resource menu tab.
Step 5
Select the Leveling Order to Id only.
Step 6
Clear the Leveling Can Adjust Individual Assignments On A Task checkbox.
Step 7
Clear the Leveling Can Create Splits In Remaining Work checkbox.
Step 8
Now click the Level All button.