How To Level Project Schedule In Project 2010

This article shows how to level project schedule in Project 2010.
  • 1782

Introduction

Process for leveling Project schedule in project 2010 is given below.

Step 1

Confirm tasks are in priority order in the WBS hierarchy.

Step 2

Confirm only one resource is assigned to each task.

Step 3

Now select the Resource menu tab.

 select-resource-tab-in-project 2010.jpg

Step 4

Then select the Leveling Options from the resource menu tab.

 select-leveling-option-in-project 2010.jpg

Step 5

Select the Leveling Order to Id only.

 leveling-order-in-project 2010.jpg

Step 6

Clear the Leveling Can Adjust Individual Assignments On A Task checkbox.

 clear-task-checkbox-in-project 2010.jpg

Step 7

Clear the Leveling Can Create Splits In Remaining Work checkbox.

 clear-work-checkbox-in-project 2010.jpg

Step 8

Now click the Level All button.

 level-all-resource-in-project 2010.jpg