How To View Calendar Details In Project 2010

This article shows how to view calendar details in Project 2010.
  • 1916

Introduction

Process for viewing calendar details in Microsoft Project 2010 is given below.

Step 1

On the View tab, click on Change Working Time.

 change-working-time-in-project 2010.jpg

Step 2

Select the name of the calendar from the drop down list.

 choose-calender-type-in-project 2010.jpg

Step 3

To create new calendar click on Create New Calendar box.

 create-new-calendar-in-project 2010.jpg

Step 4

Click on any day in a grid to see the working time of that day.

 view-working-time-in-project 2010.jpg