Set Working Time For The Resources In Project 2010
This article explains how to set working time for the resources in Project 2010.
Introduction
Process for set working time for resources in Project 2010 is given below.
Step 1
On the Project menu and in the Properties group click on Change Working Time tab.
Step 2
In the For Calendar list click the calendar that you want to change.
Step 3
To change the default work week for either the project calendar, resource calendar or for a new one you created, click on Work Weeks tab.
Step 4
On the Work Weeks tab you can choose or create an additional work week schedule for a range of days that differ from the default work day.
Step 5
In the Working Times table type a descriptive name in the Name column and then enter the start times and the finish times for the time during which the additional scheduling will occur.
Step 6
Now click on Details tab.
Step 7
In the Details For dialog box select in turn each day you want to change from a working day to non working day or vice versa.
Step 8
Then select one of the following.
1. Choose the days that should use the default working times, which are 8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM, monday through friday and non working time on weekends.
2. Choose the days on which no work can be scheduled.
3. To set the working times for selected days throughout the schedule type the times that you want work to start in the From boxes and the times you want work to end in the To boxes.