Set Working Time For The Resources In Project 2010

This article explains how to set working time for the resources in Project 2010.
  • 2687

Introduction

Process for set working time for resources in Project 2010 is given below.

Step 1

On the Project menu and in the Properties group click on Change Working Time tab.

 select-change-working-time-in-project 2010.jpg

Step 2

In the For Calendar list click the calendar that you want to change.

 select-calendar-type-in-project 2010.jpg

Step 3

To change the default work week for either the project calendar, resource calendar or for a new one you created, click on Work Weeks tab.

 select-work-weeks-in-project 2010.jpg

Step 4

On the Work Weeks tab you can choose or create an additional work week schedule for a range of days that differ from the default work day.

Step 5

In the Working Times table type a descriptive name in the Name column and then enter the start times and the finish times for the time during which the additional scheduling will occur.

 enter-name-in-project 2010.jpg

Step 6

Now click on Details tab.

 details-in-project 2010.jpg

Step 7

In the Details For dialog box select in turn each day you want to change from a working day to non working day or vice versa.

 select-each-day-time-in-project 2010.jpg

Step 8

Then select one of the following.

1. Choose the days that should use the default working times, which are 8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM, monday through friday and non working time on weekends.

 default-time-in-project 2010.jpg

2. Choose the days on which no work can be scheduled.

 nonworking-timing-in-project 2010.jpg

3. To set the working times for selected days throughout the schedule type the times that you want work to start in the From boxes and the times you want work to end in the To boxes.

 set-timing-in-project 2010.jpg